September Bond Progress Update

We’re excited to share that construction is progressing smoothly, and we’re seeing some big changes across the job site!

Building Progress

  • The building’s final exterior walls are going up, and within the next couple of weeks, it’ll be fully enclosed.
  • Brick veneer is being installed around the outside, with the weight room’s exterior brick almost finished.

Interior Updates

  • Sheetrock is up on the interior walls, and some areas are already getting primer and paint! The ceiling paint is more than halfway done.
  • Cabinets are being installed in the science classrooms.

Gym/Band/Cafeteria

  • The gym bleachers are installed, and the roofing for both the gym and band hall is nearly finished.
  • Glass windows are installed in the concession/cafeteria area, and tile is being installed in the new high school kitchen and locker rooms.

Electrical

  • The main switchgear will be installed next week, a major step toward providing power to the new spaces!

This is just a snapshot of all the progress happening on the high school additions. We’re so excited to watch it all come together, and we’ll keep you updated as we move forward!