Click here to see the Milestone Schedule as of 3/22/2023
Conceptual Site Plan
Proposition A
Classrooms, labs, restrooms, and cafeteria additions and renovations: $9,500,000
- Address the growing student population
- Allow for additional science courses
Rerouting of buses and cars for traffic flow efficiency and additional parking: $750,000
- New routes for drop-off and pick-up
- Paving of grassy area in front of Buffalo Stadium currently being used as overflow parking.
Relocating baseball and softball fields to address current and future high school expansion: $6,500,000
- Relocation will free up space for a high school science wing, CTE health science room and additional restrooms.
- Added space for future high school additions and parking areas.
Safety and security upgrades: $600,000
- Secured vestibule at the high school
- New intercom system
- Unified key system
Band hall expansion: $2,500,000
- Increased space for practice and shorter travel time for middle school students.
Career and technical education expansion: $3,000,000
- Additional space for current and future CTE courses
New multipurpose facility: $13,250,000
- Relieves strain on master scheduling
- Additional indoor space for sports, clubs, pep rallies, graduations, and more.
New locker rooms, weight room, and storage: $4,900,000
- Create appropriate space for a growing athletic program
Proposition B - Completed
Press box, restroom and concession upgrades: $2,100,000
- Upgrades to address aging and undersized facilities
Turf, drainage, and field improvements: $1,200,000
- Safer area for games, practices, and competitions
ADA compliance: $600,000
- Allows all fans to access our facilities